| Queue ID | C01-2029 |
|---|---|
| Project name | Haviland - Timber Switch 138 kV & Logtown - North Delphos 138 kV |
| Status (as published) | Active |
| Substation | Haviland - Timber Switch & Logtown - North Delphos |
| Point of interconnection | Haviland - Timber Switch 138 kV & Logtown - North Delphos 138 kV |
| County | Paulding |
| State | OH |
| Voltage | 138 kV |
| Capacity | 289.3 MW |
| Resource (as published) | Natural Gas |
| Resource category | Gas (normalised for filtering) |
| Target commercial operation | 2031-05-31 |
| Source dataset | cycle |
Additional filed fields
| Developer | Cortex Sycamore, LLC |
|---|---|
| Transmission Owner | AEP |
| Project Type | Generation Interconnection |
| Cycle | C01 |
| Stage | Phase 1 |
| Mw Energy | 300.0 |
| Mw Capacity | 289.3 |
| Mfo | 300.0 |
| Submitted Date | 4/25/2026 |
| Last Updated | 6/25/2026 |