Boydton DP 115 kV

PJM queue ID C01-1987 Terminal status

Queue IDC01-1987
Project nameBoydton DP 115 kV
Status (as published)Withdrawn
SubstationBoydton DP
Point of interconnectionBoydton DP 115 kV
CountyMecklenburg
StateVA
Voltage115 kV
Capacity70 MW
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2030-10-31
Source datasetcycle

Tracked changes

1 change observed between weekly snapshots of the PJM queue since PJM tracking began on August 27, 2026. MW is nameplate as filed; for a capacity revision it is the change, not the new total.

DetectedChangeMWStatus was → now
2026-10-05 Terminal status 70 Active → Withdrawn

Full change log →

Additional filed fields

DeveloperOriden LLC
Transmission OwnerDominion
Project TypeGeneration Interconnection
CycleC01
StagePhase 1
Mw Energy100.0
Mw Capacity70.0
Mfo100.0
Submitted Date4/27/2026
Withdrawn Date9/28/2026
Withdrawn RemarksCIW
Last Updated6/24/2026