Claysburg 115 kV

PJM queue ID C01-1957 Terminal status

Queue IDC01-1957
Project nameClaysburg 115 kV
Status (as published)Withdrawn
SubstationClaysburg
Point of interconnectionClaysburg 115 kV
CountyBlair
StatePA
Voltage115 kV
Capacity289.3 MW
Resource (as published)Natural Gas
Resource categoryGas (normalised for filtering)
Target commercial operation2031-05-31
Source datasetcycle

Tracked changes

1 change observed between weekly snapshots of the PJM queue since PJM tracking began on August 27, 2026. MW is nameplate as filed; for a capacity revision it is the change, not the new total.

DetectedChangeMWStatus was → now
2026-10-05 Terminal status 289.3 Active → Withdrawn

Full change log →

Additional filed fields

DeveloperCortex Sycamore, LLC
Transmission OwnerPENELEC
Project TypeGeneration Interconnection
CycleC01
StagePhase 1
Mw Energy300.0
Mw Capacity289.3
Mfo300.0
Submitted Date4/25/2026
Withdrawn Date9/28/2026
Withdrawn RemarksCIW
Last Updated6/5/2026

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.