Shiloh DP - Conetoe Tap 115 kV

PJM queue ID C01-1918

Queue IDC01-1918
Project nameShiloh DP - Conetoe Tap 115 kV
Status (as published)Active
SubstationShiloh DP - Conetoe Tap
Point of interconnectionShiloh DP - Conetoe Tap 115 kV
CountyPitt
StateNC
Voltage115 kV
Capacity179 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2029-09-01
Source datasetcycle

Additional filed fields

DeveloperKaneeta Solar LLC
Transmission OwnerDominion
Project TypeGeneration Interconnection
CycleC01
StagePhase 1
Mw Energy185.0
Mw Capacity179.0
Mfo185.0
Submitted Date4/27/2026
Last Updated6/21/2026