North Shenandoah - Merck 115 kV

PJM queue ID C01-1914 Terminal status

Queue IDC01-1914
Project nameNorth Shenandoah - Merck 115 kV
Status (as published)Withdrawn
SubstationNorth Shenandoah - Merck
Point of interconnectionNorth Shenandoah - Merck 115 kV
CountyRockingham
StateVA
Voltage115 kV
Capacity110 MW
Resource (as published)Solar,Storage,Hybrid
Resource categoryHybrid (normalised for filtering)
Target commercial operation2030-12-31
Source datasetcycle

Additional filed fields

DeveloperRenewable Energy Services LLC
Transmission OwnerDominion
Project TypeGeneration Interconnection
CycleC01
StageApplication Review
Mw Energy110.0
Mw Capacity110.0
Mfo110.0
Submitted Date4/27/2026
Withdrawn Date8/3/2026
Withdrawn RemarksCIW
Last Updated6/15/2026