Substation Scout

Piney Grove - Loretto 138 kV

PJM queue ID C01-1912

Queue IDC01-1912
Project namePiney Grove - Loretto 138 kV
Status (as published)Active
SubstationPiney Grove - Loretto
Point of interconnectionPiney Grove - Loretto 138 kV
CountySomerset
StateMD
Voltage138 kV
Capacity70 MW
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2030-07-17
Source datasetcycle

Additional filed fields

DeveloperRenewable Energy Services LLC
Transmission OwnerDPL
Project TypeGeneration Interconnection
CycleC01
StagePhase 1
Mw Energy70.0
Mw Capacity70.0
Mfo70.0
Submitted Date4/27/2026
Last Updated6/4/2026

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.