Substation Scout

Alleghany - Pride 115 kV

PJM queue ID C01-1791

Queue IDC01-1791
Project nameAlleghany - Pride 115 kV
Status (as published)Active
SubstationAlleghany - Pride
Point of interconnectionAlleghany - Pride 115 kV
CountySomerset
StatePA
Voltage115 kV
Capacity100 MW
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2031-01-01
Source datasetcycle

Additional filed fields

DeveloperTurnpike Solar, LLC
Transmission OwnerPENELEC
Project TypeGeneration Interconnection
CycleC01
StagePhase 1
Mw Energy100.0
Mw Capacity100.0
Mfo100.0
Submitted Date4/27/2026
Last Updated6/8/2026

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.