LadySmith - Possum Point 500 kV

PJM queue ID C01-1735 Terminal status

Queue IDC01-1735
Project nameLadySmith - Possum Point 500 kV
Status (as published)Withdrawn
SubstationLadySmith - Possum Point
Point of interconnectionLadySmith - Possum Point 500 kV
CountyPrince William County
StateVA
Voltage500 kV
Capacity750 MW
Resource (as published)Fuel Cell,Natural Gas,Nuclear,Hybrid
Resource categoryHybrid (normalised for filtering)
Target commercial operation2030-01-01
Source datasetcycle

Additional filed fields

DeveloperOklo Power LLC
Transmission OwnerDominion
Project TypeGeneration Interconnection
CycleC01
StageApplication Review
Mw Energy750.0
Mw Capacity750.0
Mfo750.0
Submitted Date4/27/2026
Withdrawn Date8/3/2026
Withdrawn RemarksCMN
Last Updated6/1/2026

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.