Substation Scout

Papermill Tap - Harmony Village 230 kV

PJM queue ID C01-1604 Terminal status

Queue IDC01-1604
Project namePapermill Tap - Harmony Village 230 kV
Status (as published)Withdrawn
SubstationPapermill Tap - Harmony Village
Point of interconnectionPapermill Tap - Harmony Village 230 kV
CountyNorthampton
StateNC
Voltage230 kV
Capacity50 MW
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2032-12-31
Source datasetcycle

Tracked changes

1 change observed between weekly snapshots of the PJM queue since PJM tracking began on August 27, 2026. MW is nameplate as filed; for a capacity revision it is the change, not the new total.

DetectedChangeMWStatus was → now
2026-09-28 Terminal status 50 Active → Withdrawn

Full change log →

Additional filed fields

DeveloperScout Solar LandCo, LLC
Transmission OwnerDominion
Project TypeGeneration Interconnection
CycleC01
StagePhase 1
Mw Energy50.0
Mw Capacity50.0
Mfo200.0
Submitted Date4/27/2026
Withdrawn Date9/25/2026
Withdrawn RemarksCIW
Last Updated5/29/2026

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.