Pontiac Red 345kV - Dresden 345 kV

PJM queue ID C01-1581

Queue IDC01-1581
Project namePontiac Red 345kV - Dresden 345 kV
Status (as published)Active
SubstationPontiac Red - Dresden
Point of interconnectionPontiac Red 345kV - Dresden 345 kV
CountyGrundy
StateIL
Voltage345 kV
Capacity210 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2032-12-31
Source datasetcycle

Additional filed fields

DeveloperBlue Sky Solar Energy, LLC
Transmission OwnerComEd
Project TypeGeneration Interconnection
CycleC01
StagePhase 1
Mw Energy350.0
Mw Capacity210.0
Mfo350.0
Submitted Date4/27/2026
Last Updated6/18/2026