Paige - St. Johns 230 kV

PJM queue ID C01-1449

Queue IDC01-1449
Project namePaige - St. Johns 230 kV
Status (as published)Active
SubstationPaige - St. Johns
Point of interconnectionPaige - St. Johns 230 kV
CountyCaroline
StateVA
Voltage230 kV
Capacity500 MW
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2033-03-01
Source datasetcycle

Additional filed fields

DeveloperJuneberry Energy Storage LLC
Transmission OwnerDominion
Project TypeGeneration Interconnection
CycleC01
StagePhase 1
Mw Energy500.0
Mw Capacity500.0
Mfo500.0
Submitted Date4/24/2026
Last Updated6/1/2026