Substation Scout

Jetersville-Ponton 115 kV

PJM queue ID C01-1347 Terminal status

Queue IDC01-1347
Project nameJetersville-Ponton 115 kV
Status (as published)Withdrawn
SubstationJetersville-Ponton
Point of interconnectionJetersville-Ponton 115 kV
CountyAmelia
StateVA
Voltage115 kV
Capacity12 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2028-12-31
Source datasetcycle

Additional filed fields

DeveloperAmelia Energy Facility, LLC
Transmission OwnerDominion
Project TypeGeneration Interconnection
CycleC01
StageApplication Review
Mw Energy20.0
Mw Capacity12.0
Mfo126.0
Submitted Date4/27/2026
Withdrawn Date8/3/2026
Withdrawn RemarksCIW
Last Updated4/27/2026

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.