Substation Scout

National - Mitchell 138 kV

PJM queue ID C01-1345 Terminal status

Queue IDC01-1345
Project nameNational - Mitchell 138 kV
Status (as published)Withdrawn
SubstationNational - Mitchell
Point of interconnectionNational - Mitchell 138 kV
CountyMadison
StateOH
Voltage138 kV
Capacity120 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2030-09-30
Source datasetcycle

Tracked changes

1 change observed between weekly snapshots of the PJM queue since PJM tracking began on August 27, 2026. MW is nameplate as filed; for a capacity revision it is the change, not the new total.

DetectedChangeMWStatus was → now
2026-09-23 Terminal status 120 Active → Withdrawn

Full change log →

Additional filed fields

DeveloperOak Run II Solar Project, LLC
Transmission OwnerATSI
Project TypeGeneration Interconnection
CycleC01
StagePhase 1
Mw Energy200.0
Mw Capacity120.0
Mfo200.0
Submitted Date4/27/2026
Withdrawn Date9/22/2026
Withdrawn RemarksCIW
Last Updated5/12/2026

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.