Talbert - Hawkins Gate 230 kV & Talbert to Morgantown 230 kV

PJM queue ID C01-1338 Terminal status

Queue IDC01-1338
Project nameTalbert - Hawkins Gate 230 kV & Talbert to Morgantown 230 kV
Status (as published)Withdrawn
SubstationTalbert - Hawkins Gate & Talbert to Morgantown
Point of interconnectionTalbert - Hawkins Gate 230 kV & Talbert to Morgantown 230 kV
CountyCharles
StateMD
Voltage230 kV
Capacity510 MW
Resource (as published)Natural Gas
Resource categoryGas (normalised for filtering)
Target commercial operation2031-06-30
Source datasetcycle

Tracked changes

1 change observed between weekly snapshots of the PJM queue since PJM tracking began on August 27, 2026. MW is nameplate as filed; for a capacity revision it is the change, not the new total.

DetectedChangeMWStatus was → now
2026-09-28 Terminal status 510 Active → Withdrawn

Full change log →

Additional filed fields

DeveloperOld Line Reserve Energy, LLC
Transmission OwnerPEPCO
Project TypeGeneration Interconnection
CycleC01
StagePhase 1
Mw Energy510.0
Mw Capacity510.0
Mfo510.0
Submitted Date4/27/2026
Withdrawn Date9/25/2026
Withdrawn RemarksCIW
Last Updated6/15/2026