Substation Scout

Garvers Ferry Jct - Braeburn Steel 25 kV

PJM queue ID C01-1123 Terminal status

Queue IDC01-1123
Project nameGarvers Ferry Jct - Braeburn Steel 25 kV
Status (as published)Withdrawn
SubstationGarvers Ferry Jct - Braeburn Steel
Point of interconnectionGarvers Ferry Jct - Braeburn Steel 25 kV
CountyWestmoreland
StatePA
Voltage25 kV
Capacity9.6 MW
Resource (as published)Hydro
Resource categoryHydro (normalised for filtering)
Target commercial operation2031-05-31
Source datasetcycle

Additional filed fields

DeveloperAllegheny Hydro Group Lock And Dam 4, Inc
Transmission OwnerAPS
Project TypeGeneration Interconnection
CycleC01
StageApplication Review
Mw Energy9.55
Mw Capacity9.55
Mfo9.55
Submitted Date4/27/2026
Withdrawn Date8/3/2026
Withdrawn RemarksCMN
Last Updated5/27/2026