Sewickley - Crescent 23 kV

PJM queue ID C01-1121 Terminal status

Queue IDC01-1121
Project nameSewickley - Crescent 23 kV
Status (as published)Withdrawn
SubstationSewickley - Crescent
Point of interconnectionSewickley - Crescent 23 kV
CountyAllegheny
StatePA
Voltage23 kV
Capacity8.8 MW
Resource (as published)Hydro
Resource categoryHydro (normalised for filtering)
Target commercial operation2030-09-30
Source datasetcycle

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

DeveloperDashields Hydropower Corporation
Transmission OwnerDL
Project TypeGeneration Interconnection
CycleC01
StageApplication Review
Mw Energy8.75
Mw Capacity8.75
Mfo8.75
Submitted Date4/27/2026
Withdrawn Date8/3/2026
Withdrawn RemarksCMN
Last Updated6/25/2026

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.