Substation Scout

Auburn - Clipper 69 kV

PJM queue ID C01-1041 Terminal status

Queue IDC01-1041
Project nameAuburn - Clipper 69 kV
Status (as published)Withdrawn
SubstationAuburn - Clipper
Point of interconnectionAuburn - Clipper 69 kV
CountyDeKalb
StateIN
Voltage69 kV
Capacity10.1 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2026-04-27
Source datasetcycle

Additional filed fields

DeveloperAuburn Renewables LLC
Transmission OwnerAEP
Project TypeGeneration Interconnection
CycleC01
StageApplication Review
Mw Energy11.0
Mw Capacity10.12
Mfo11.0
Submitted Date4/23/2026
Withdrawn Date8/3/2026
Withdrawn RemarksCMN
Last Updated6/25/2026

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.