Raritan River 230 kV

PJM queue ID C01-1012 Terminal status

Queue IDC01-1012
Project nameRaritan River 230 kV
Status (as published)Withdrawn
SubstationRaritan River
Point of interconnectionRaritan River 230 kV
CountyMiddlesex
StateNJ
Voltage230 kV
Capacity0 MW (0 MW as filed — net change or energy-only)
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2028-11-24
Source datasetcycle

Additional filed fields

DeveloperHeritage Power Marketing, LLC
Transmission OwnerJCPL
Project TypeGeneration Interconnection
CycleC01
StageApplication Submission
Mw Energy0.0
Mw Capacity0.0
Mfo211.3
Submitted Date5/30/2025
Withdrawn Date7/10/2025
Withdrawn RemarksCIW
Last Updated5/30/2025