Substation Scout

Perryman 230kV/115kV

PJM queue ID B29 Terminal status

Queue IDB29
Project namePerryman 230kV/115kV
Status (as published)Withdrawn
SubstationPerryman /
Point of interconnectionPerryman 230kV/115kV
CountyHarford
StateMD
Voltage230 kV
Capacity750 MW
Resource (as published)Natural Gas
Resource categoryGas (normalised for filtering)
Target commercial operationNot reported
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy750
Mw Capacity750
Mfo750
Withdrawn Date4/17/2001

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.