Substation Scout

Maysville 138 kV

PJM queue ID AI2-467 Terminal status

Queue IDAI2-467
Project nameMaysville 138 kV
Status (as published)Withdrawn
SubstationMaysville
Point of interconnectionMaysville 138 kV
CountyMercer
StatePA
Voltage138 kV
Capacity5.8 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2027-05-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy0
Mw Capacity5.8
Mfo20
Withdrawn Date3/11/2026

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.