Substation Scout

Wilton Center - Loretto 345 kV(CIR Increase)

PJM queue ID AI2-461 Terminal status

Queue IDAI2-461
Project nameWilton Center - Loretto 345 kV(CIR Increase)
Status (as published)Withdrawn
SubstationWilton Center - Loretto (CIR Increase)
Point of interconnectionWilton Center - Loretto 345 kV(CIR Increase)
CountyKankakee
StateIL
Voltage345 kV
Capacity173 MW
Resource (as published)Wind
Resource categoryWind (normalised for filtering)
Target commercial operation2026-05-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy0
Mw Capacity173
Mfo850

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.