Substation Scout

W4-005 345kV (CIR Increase)

PJM queue ID AI2-455 Terminal status

Queue IDAI2-455
Project nameW4-005 345kV (CIR Increase)
Status (as published)Withdrawn
SubstationW4-005 (CIR Increase)
Point of interconnectionW4-005 345kV (CIR Increase)
CountyUnion
StatePA
Voltage345 kV
Capacity162.8 MW
Resource (as published)Wind
Resource categoryWind (normalised for filtering)
Target commercial operation2023-03-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy0
Mw Capacity162.8
Mfo306

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.