Parsons - William 138 kV

PJM queue ID AI2-445 Terminal status

Queue IDAI2-445
Project nameParsons - William 138 kV
Status (as published)Withdrawn
SubstationParsons - William
Point of interconnectionParsons - William 138 kV
CountyTucker
StateWV
Voltage138 kV
Capacity128.8 MW
Resource (as published)Solar; Storage
Resource categoryHybrid (normalised for filtering)
Target commercial operation2026-03-08
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy148
Mw Capacity128.8
Mfo148
Withdrawn Date1/22/2026