Substation Scout

North Longview 500 kV

PJM queue ID AI2-443 Terminal status

Queue IDAI2-443
Project nameNorth Longview 500 kV
Status (as published)Withdrawn
SubstationNorth Longview
Point of interconnectionNorth Longview 500 kV
CountyGreene
StatePA
Voltage500 kV
Capacity295 MW
Resource (as published)Solar; Storage
Resource categoryHybrid (normalised for filtering)
Target commercial operation2027-07-10
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy300
Mw Capacity295
Mfo300

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.