Substation Scout

Dubois-Curwensville 34.5 kV II

PJM queue ID AI2-433 Terminal status

Queue IDAI2-433
Project nameDubois-Curwensville 34.5 kV II
Status (as published)Withdrawn
SubstationDubois-Curwensville II
Point of interconnectionDubois-Curwensville 34.5 kV II
CountyClearfield
StatePA
Voltage34.5 kV
Capacity7.3 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2023-02-28
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy0
Mw Capacity7.28
Mfo20

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.