Substation Scout

Mendota Hills 138 kV

PJM queue ID AI2-429 Terminal status

Queue IDAI2-429
Project nameMendota Hills 138 kV
Status (as published)Withdrawn
SubstationMendota Hills
Point of interconnectionMendota Hills 138 kV
CountyLee
StateIL
Voltage138 kV
Capacity22.2 MW
Resource (as published)Wind
Resource categoryWind (normalised for filtering)
Target commercial operation2025-12-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy0
Mw Capacity22.2
Mfo76.1

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.