Substation Scout

Sowers 138 kV

PJM queue ID AI2-418 Terminal status

Queue IDAI2-418
Project nameSowers 138 kV
Status (as published)Withdrawn
SubstationSowers
Point of interconnectionSowers 138 kV
CountyAllen
StateIN
Voltage138 kV
Capacity24 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2026-12-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy0
Mw Capacity24
Mfo100
Withdrawn Date3/11/2026

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.