Lexington-Dooms 230 kV

PJM queue ID AI2-416 Terminal status

Queue IDAI2-416
Project nameLexington-Dooms 230 kV
Status (as published)Withdrawn
SubstationLexington-Dooms
Point of interconnectionLexington-Dooms 230 kV
CountyAugusta
StateVA
Voltage230 kV
Capacity50 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2026-12-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy0
Mw Capacity50
Mfo200
Withdrawn Date3/11/2026