Substation Scout

Glidden-Waterman 138 kV (CIR Increase)

PJM queue ID AI2-403 Terminal status

Queue IDAI2-403
Project nameGlidden-Waterman 138 kV (CIR Increase)
Status (as published)Withdrawn
SubstationGlidden-Waterman (CIR Increase)
Point of interconnectionGlidden-Waterman 138 kV (CIR Increase)
CountyDeKalb
StateIL
Voltage138 kV
Capacity19.5 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2026-12-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy0
Mw Capacity19.5
Mfo81.4
Withdrawn Date3/11/2026

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.