Substation Scout

Central Hardin-Stephensburg 69 kV

PJM queue ID AI2-376 Terminal status

Queue IDAI2-376
Project nameCentral Hardin-Stephensburg 69 kV
Status (as published)Withdrawn
SubstationCentral Hardin-Stephensburg
Point of interconnectionCentral Hardin-Stephensburg 69 kV
CountyHardin
StateKY
Voltage69 kV
Capacity21.8 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2025-03-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy0
Mw Capacity21.84
Mfo70
Withdrawn Date10/23/2024

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.