Substation Scout

Hope-Blevins Valley Tap 69 kV

PJM queue ID AI2-374 Terminal status

Queue IDAI2-374
Project nameHope-Blevins Valley Tap 69 kV
Status (as published)Withdrawn
SubstationHope-Blevins Valley Tap
Point of interconnectionHope-Blevins Valley Tap 69 kV
CountyBath
StateKY
Voltage69 kV
Capacity20.6 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2025-03-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy0
Mw Capacity20.59
Mfo66
Withdrawn Date3/11/2026

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.