Substation Scout

Ford - Ceddarville 138 kV

PJM queue ID AI2-348 Terminal status

Queue IDAI2-348
Project nameFord - Ceddarville 138 kV
Status (as published)Withdrawn
SubstationFord - Ceddarville
Point of interconnectionFord - Ceddarville 138 kV
CountyClermont
StateOH
Voltage138 kV
Capacity17.4 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2025-12-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy0
Mw Capacity17.4
Mfo152.2
Withdrawn Date3/17/2026

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.