Cowansville Junction – Long Run Tap 25 kV

PJM queue ID AI2-324 Terminal status

Queue IDAI2-324
Project nameCowansville Junction – Long Run Tap 25 kV
Status (as published)Withdrawn
SubstationCowansville Junction – Long Run Tap
Point of interconnectionCowansville Junction – Long Run Tap 25 kV
CountyArmstrong
StatePA
Voltage25 kV
Capacity3.7 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2025-06-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy0
Mw Capacity3.72
Mfo14.7
Withdrawn Date1/15/2026