Substation Scout

Molecreek 345kV (CIR Increase)

PJM queue ID AI2-314 Terminal status

Queue IDAI2-314
Project nameMolecreek 345kV (CIR Increase)
Status (as published)Withdrawn
SubstationMolecreek (CIR Increase)
Point of interconnectionMolecreek 345kV (CIR Increase)
CountyWoodford
StateIL
Voltage345 kV
Capacity27 MW
Resource (as published)Wind
Resource categoryWind (normalised for filtering)
Target commercial operation2025-12-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy0
Mw Capacity27
Mfo100

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.