Edinboro South-Venango Junction 115 kV IV

PJM queue ID AI2-293 Terminal status

Queue IDAI2-293
Project nameEdinboro South-Venango Junction 115 kV IV
Status (as published)Withdrawn
SubstationEdinboro South-Venango Junction IV
Point of interconnectionEdinboro South-Venango Junction 115 kV IV
CountyCrawford
StatePA
Voltage115 kV
Capacity8.2 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2025-12-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy0
Mw Capacity8.16
Mfo116.5

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.