Greenfield 69 kV

PJM queue ID AI2-250 Terminal status

Queue IDAI2-250
Project nameGreenfield 69 kV
Status (as published)Withdrawn
SubstationGreenfield
Point of interconnectionGreenfield 69 kV
CountyFayette
StateOH
Voltage69 kV
Capacity10 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2024-05-31
Source datasetserial

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy0
Mw Capacity10
Mfo48