Substation Scout

TSS 968 345 kV (CIR Increase)

PJM queue ID AI2-245 Terminal status

Queue IDAI2-245
Project nameTSS 968 345 kV (CIR Increase)
Status (as published)Withdrawn
SubstationTSS 968 (CIR Increase)
Point of interconnectionTSS 968 345 kV (CIR Increase)
CountyWoodford
StateIL
Voltage345 kV
Capacity55.2 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2028-06-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy0
Mw Capacity55.2
Mfo200
Withdrawn Date3/11/2026

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.