Substation Scout

Cloverdale-Burlington Height 138 kV

PJM queue ID AI2-231A Terminal status

Queue IDAI2-231A
Project nameCloverdale-Burlington Height 138 kV
Status (as published)Withdrawn
SubstationCloverdale-Burlington Height
Point of interconnectionCloverdale-Burlington Height 138 kV
CountyBotetourt
StateVA
Voltage138 kV
Capacity60 MW
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2023-10-22
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy0
Mw Capacity60
Mfo100
Withdrawn Date3/11/2026

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.