Substation Scout

Jug Street 138 kV

PJM queue ID AI2-226 Terminal status

Queue IDAI2-226
Project nameJug Street 138 kV
Status (as published)Withdrawn
SubstationJug Street
Point of interconnectionJug Street 138 kV
CountyLicking
StateOH
Voltage138 kV
Capacity120 MW
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2022-08-22
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy0
Mw Capacity120
Mfo200

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.