Substation Scout

WinFall-Chowan 230kV

PJM queue ID AI2-223 Terminal status

Queue IDAI2-223
Project nameWinFall-Chowan 230kV
Status (as published)Withdrawn
SubstationWinFall-Chowan
Point of interconnectionWinFall-Chowan 230kV
CountyChowan
StateNC
Voltage230 kV
Capacity56.4 MW
Resource (as published)Wind
Resource categoryWind (normalised for filtering)
Target commercial operation2024-05-28
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy0
Mw Capacity56.4
Mfo189

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.