Beaver-Davis Besse 345 kV II

PJM queue ID AI2-220 Terminal status

Queue IDAI2-220
Project nameBeaver-Davis Besse 345 kV II
Status (as published)Withdrawn
SubstationBeaver-Davis Besse II
Point of interconnectionBeaver-Davis Besse 345 kV II
CountyErie
StateOH
Voltage345 kV
Capacity103.1 MW
Resource (as published)Wind
Resource categoryWind (normalised for filtering)
Target commercial operation2024-10-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy0
Mw Capacity103.1
Mfo297.66

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.