Scottsville - Bremo 138 kV

PJM queue ID AI2-214 Terminal status

Queue IDAI2-214
Project nameScottsville - Bremo 138 kV
Status (as published)Withdrawn
SubstationScottsville - Bremo
Point of interconnectionScottsville - Bremo 138 kV
CountyBuckingham
StateVA
Voltage138 kV
Capacity55 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2025-12-12
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy0
Mw Capacity55
Mfo149.5