Substation Scout

Bennett - Farmingdale 34.5 kV

PJM queue ID AI2-202 Terminal status

Queue IDAI2-202
Project nameBennett - Farmingdale 34.5 kV
Status (as published)Withdrawn
SubstationBennett - Farmingdale
Point of interconnectionBennett - Farmingdale 34.5 kV
CountyMonmouth
StateNJ
Voltage34.5 kV
Capacity1.2 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2023-03-11
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy0
Mw Capacity1.2
Mfo2

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.