Substation Scout

Clinton - Stuart 345 kV

PJM queue ID AI2-165 Terminal status

Queue IDAI2-165
Project nameClinton - Stuart 345 kV
Status (as published)Withdrawn
SubstationClinton - Stuart
Point of interconnectionClinton - Stuart 345 kV
CountyClinton
StateOH
Voltage345 kV
Capacity72 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2023-12-25
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy0
Mw Capacity72
Mfo300

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.