Substation Scout

Eldean 138 kV

PJM queue ID AI2-159 Terminal status

Queue IDAI2-159
Project nameEldean 138 kV
Status (as published)Withdrawn
SubstationEldean
Point of interconnectionEldean 138 kV
CountyMiami
StateOH
Voltage138 kV
Capacity43.5 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2027-12-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy0
Mw Capacity43.52
Mfo232
Withdrawn Date1/21/2026

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.