Substation Scout

Fentress - Sligo 230kV (CIR Increase)

PJM queue ID AI2-158 Terminal status

Queue IDAI2-158
Project nameFentress - Sligo 230kV (CIR Increase)
Status (as published)Withdrawn
SubstationFentress - Sligo (CIR Increase)
Point of interconnectionFentress - Sligo 230kV (CIR Increase)
CountyCity of Chesapeake
StateVA
Voltage230 kV
Capacity48 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2024-12-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy0
Mw Capacity48
Mfo192
Withdrawn Date9/12/2023

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.