Substation Scout

Moshannon-Milesburg 230 kV IX

PJM queue ID AI2-154 Terminal status

Queue IDAI2-154
Project nameMoshannon-Milesburg 230 kV IX
Status (as published)Withdrawn
SubstationMoshannon-Milesburg IX
Point of interconnectionMoshannon-Milesburg 230 kV IX
CountyCentre
StatePA
Voltage230 kV
Capacity24 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2025-12-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy0
Mw Capacity24
Mfo100
Withdrawn Date1/21/2026

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.