Substation Scout

Stockton 138 kV

PJM queue ID AI2-137 Terminal status

Queue IDAI2-137
Project nameStockton 138 kV
Status (as published)Withdrawn
SubstationStockton
Point of interconnectionStockton 138 kV
CountyHenry
StateVA
Voltage138 kV
Capacity21.6 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2022-12-31
Source datasetserial

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy0
Mw Capacity21.6
Mfo90

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.