Substation Scout

Ada-Dunkirk 69kV

PJM queue ID AI2-107 Terminal status

Queue IDAI2-107
Project nameAda-Dunkirk 69kV
Status (as published)Withdrawn
SubstationAda-Dunkirk
Point of interconnectionAda-Dunkirk 69kV
CountyHardin
StateOH
Voltage69 kV
Capacity31.7 MW
Resource (as published)Wind
Resource categoryWind (normalised for filtering)
Target commercial operation2023-02-27
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy0
Mw Capacity31.7
Mfo66

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.