Pontiac MidPoint-Brokaw 345kV

PJM queue ID AI2-106 Terminal status

Queue IDAI2-106
Project namePontiac MidPoint-Brokaw 345kV
Status (as published)Withdrawn
SubstationPontiac MidPoint-Brokaw
Point of interconnectionPontiac MidPoint-Brokaw 345kV
CountyLivingston
StateIL
Voltage345 kV
Capacity106.4 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2023-02-27
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy0
Mw Capacity106.4
Mfo200